Lake Fort Smith Water Transmission Line Phase 2A1-2 federal funding request
Fort Smith is pulling in major federal dollars for water: $12 million from Senator Boozman for the Lake Fort Smith transmission line (no local match needed) and $3 million from HUD for neighborhood water lines. The transmission line repair overall is estimated at $300-500 million.
Consent Decree Program Management (Arcadis)
The city is hiring a national firm to manage the remaining nine years of federally mandated sewer work, funded by up to $385 million in sales tax bonds. Directors questioned whether the $2.474M first-year price will pay for itself in savings and accountability.
Denali lagoon-cleaning contract and competitive bidding concerns
The city awarded a $919,000 lagoon-cleaning contract to Denali Water Solutions even though it was the only bidder, prompting residents to demand broader outreach to firms serving other Arkansas cities. Staff committed to bidding next year's lagoon work earlier, advertising more widely, and contacting companies residents identified.
2017 SSA Remedial Measures sewer projects and consent decree compliance
Several resolutions advanced the city's federally driven sewer work: easement purchases in three sub-basins, a change order cutting over $1 million from the pipe-bursting contract, and a final payment closing out that project. Utility customers fund this through the 5/8% sales tax and bond funds.
Massard Water Reclamation Facility Improvements (Project No. 25-15-ED1)
A $8.575 million engineering contract with Garver, LLC for upgrades to the Massard wastewater treatment facility was back on the agenda after being tabled May 19. Directors Lee Kemp and Andre Good had pushed for further discussion at a study session.
Utility billing audit and $0 bills mystery
The Board looked at switching water bills from CCF (hundred cubic feet) to gallons so bills are easier to understand. It's on hold — every meter in the city would need replacing, and that costs serious money.
Sanitary sewer remediation program funding
The board approved roughly $11 million in contracts, change orders, and engineering for ongoing sanitary sewer fixes required under the federal consent decree — work funded by sales tax and 2025 bonds.
Stormwater drainage problems near South 28th Street and Grinnell Avenue
A neighboring property owner says decades-old drainage failures — sinkholes, an undersized culvert and an eroding ditch — have never been fixed, and fears the nursing home addition will make it worse. The city's engineer suspects a collapsed or clogged city pipe may be the real culprit. The commission required a drainage study before any building permit.
Senior citizen water rate assistance
Directors are considering freezing water rates for seniors on fixed incomes. They want staff to bring feasible options to the June 9 study session before deciding.
2022 SSA Remedial Measures, Sub-Basin S005 (engineering amendment and easements)
Two resolutions supported the ongoing consent-decree-related sewer work in Sub-Basin S005: a $12,000 contract extension with Halff Associates and $18,312.18 in easement purchases from 37 property owners, with eminent domain as a last resort.
Wholesale wastewater agreement with Town of Arkoma
Fort Smith has been treating Arkoma's sewage at a steep discount proposal ($3.60/CCF vs. the $9.05 residents pay), and Arkoma owes about $141,000. Directors are weighing fairness to Fort Smith ratepayers, precedent for other towns, and whether the deal conflicts with the federal consent decree.
SSA consent decree remediation projects (Sub-Basins P008 and FL02)
Two long-tabled sewer remediation contracts will be split into phases and rebid, likely to control costs. Work continues under the federal consent decree.