2022 SSA Remedial Measures, Sub-Basin S005 (engineering amendment and easements)
Fort Smith
Summary
Two resolutions supported the ongoing consent-decree-related sewer work in Sub-Basin S005: a $12,000 contract extension with Halff Associates and $18,312.18 in easement purchases from 37 property owners, with eminent domain as a last resort.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jun 2, 2026.
Impact analysis
Combined cost of the amendment and easements was about $30,312, from the 2025 Sales and Use Tax Bonds.
Property owners in the affected sewer basin and the broader community through consent decree compliance.
The 37 affected property owners would grant easements across their land, though they were to be compensated.
Mentions & discussions (3)
Board of Directors - Regular Meeting - Jun 2, 2026
Two resolutions supported the ongoing consent-decree-related sewer work in Sub-Basin S005: a $12,000 contract extension with Halff Associates and $18,312.18 in easement purchases from 37 property owners, with eminent domain as a last resort.
Board of Directors - Regular Meeting - Mar 17, 2026
Several agenda items advance sanitary sewer work: easement purchases from Morris Drive homeowners, an engineering contract for Basin 12 Sub-Basin P006, and the B Street South Sewer Upgrades.
Board of Directors - Regular Meeting - Jan 20, 2026
Two change orders under the consent-decree-related sewer work: $95,407 and 50 extra days with Forsgren, and $12,099 and 16 extra days with Patriot Utilities. These continue federally mandated sewer improvements funded by the 5/8% sales tax.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Fort Smith
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.